Events in Nur-Sultan

Expand filter

Planned works

R. Saryarka. "Astana REC" reports that " 13 " December 2019 at 16h. 50min. on TP-75., emergency and recovery work will be carried out. Without electricity there are consumers at the following addresses: Beibitshilik str., 23.

  • District САРЫАРКА, улица Бейбитшилик, ДОМ 23

Reason: emergency recovery work.

Beginning: 13.12.2019 г. 16:50 ч.
Ending: 13.12.2019 г. 18:00 ч.

Planned works

R. Saryarka. JSC "Astana-REC" reports that " 13 " December 2019 at 12h. 00 min. on TP-2102., emergency and recovery work will be carried out. Without power supply there are consumers at the following addresses: 46,48 Saryarka Ave., 33/2 Bogenbay Batyr Ave., 37 Zhenis Ave., 43/3, 43/4 , 45/3, Chapaev str.

  • District САРЫАРКА, проспект Сарыарка, ДОМ 46
  • District САРЫАРКА, проспект Сарыарка, ДОМ 48
  • District САРЫАРКА, проспект Богенбай Батыра, ДОМ 33/2
  • District САРЫАРКА, проспект Женис, ДОМ 37
  • District САРЫАРКА, проспект Женис, ДОМ 43/3
  • District САРЫАРКА, проспект Женис, ДОМ 43/4
  • District САРЫАРКА, проспект Женис, ДОМ 45/3
  • District САРЫАРКА, Чапаева, ДОМ

Reason: Emergency recovery works

Beginning: 13.12.2019 г. 14:00 ч.
Ending: 13.12.2019 г. 17:00 ч.

Planned works

Saryarka District. In connection with carrying out planned works on installation of the linear disconnector on VL-10 kV of PS "Kirov" Yach. 113, will be discontinued supply at the following addresses: PR. tlendieva, W/M "Koktal", str Turlybayeva, ul 150 years of Abai, street Arykty, Karagarga lane, St. Radlov, St Erakovic, Zh Akpaeva, KELESHEK St., St. Icary, s/O Polyanka.

Reason: Planned work

Beginning: 13.12.2019 г. 10:00 ч.
Ending: 13.12.2019 г. 14:00 ч.

Planned works

District Of Almaty. In connection with the planned works to replace the section t / Tr du-80 in The direction of zhumabeva Ave. 9/2, the supply of heat to the following addresses will be stopped: Zhumabaeva Ave. 9/2, Petrov str. 31/1.

Reason: Planned work

Beginning: 13.12.2019 г. 09:00 ч.
Ending: 13.12.2019 г. 15:00 ч.

Tracks closing/Opening

13.12. 2019. from 08-00 traffic on the highway "Nursultan-Pavlodar" for all types of vehicles is open.

Reason: Opening trails

Beginning: 13.12.2019 г. 08:00 ч.
Ending: 13.12.2019 г. 09:33 ч.

Tracks closing/Opening

13.12.2019 from 03-45 in connection with the deterioration of weather conditions (ice), closed traffic on the highway "Nursultan-Pavlodar" for all types of vehicles.

Reason: Track closures

Beginning: 13.12.2019 г. 03:45 ч.
Ending: 13.12.2019 г. 08:00 ч.

Weather conditions

The Department of emergency situations of the city of Nursultan reports that according to RSE "Kazhydromet" on December 13, ice and snowstorm are expected.

Reason: Storm warning

Beginning: 13.12.2019 г. 01:54 ч.
Ending: 13.12.2019 г. 23:54 ч.

Emergency works

Saryarka District. JSC "Astana-Teplotransit" reports that that " 12 "December 2019 at 19-30 h. there was an emergency shutdown LLP" Atlant building ran over the drainage valves in the area of 167 street. Without heat supply there are consumers at the following addresses: 167, 1, 6, 189 6/1, 6/2, 6/3 str. (ATT).ikomek109.

  • District САРЫАРКА, улица 167, ДОМ 1
  • District САРЫАРКА, улица 167, ЗДАНИЕ 6
  • District САРЫАРКА, улица 189, ДОМ 6/3
  • District САРЫАРКА, улица 189, ДОМ 6/2
  • District САРЫАРКА, улица 189, ДОМ 6/1

Reason: Emergency shutdown

Beginning: 12.12.2019 г. 19:55 ч.
Ending: 13.12.2019 г. 00:00 ч.

Emergency works

District Of Almaty. JSC "Astana-REC" reports that " 12 " December 2019 conducted emergency recovery work for 2 hours (broken cable 10kV). Without power supply there are consumers at the following addresses: Panfilov St., Nazhimidenov St., a-98 St., Deputy town (AREK). ikomek109.

Reason: Emergency recovery works

Beginning: 12.12.2019 г. 18:23 ч.
Ending: 12.12.2019 г. 20:23 ч.

Emergency works

Yesil District. GKP "Astana su Arnasy "reports that" on December 12, 2019 at 15h. 35 min., emergency recovery works are carried out due to a well leak at the address Dosmukhameduly str., 90. Without water supply there are consumers at the following addresses: MD. "Chubary", Dosmukhameduly street, Taybekov street, Atasu street, zhe Batyr street, Knyaginin street (h / s about 15) (ASA). ikomek109.

Reason: Emergency recovery works

Beginning: 12.12.2019 г. 16:24 ч.
Ending: 12.12.2019 г. 18:00 ч.